North West Crewe Package

Main construction works

The main construction works for the scheme started in May 2022. The works are being carried out by contractor Balfour Beatty on behalf of Cheshire East Council.

Construction works - 2

 

The construction works affecting existing roads will take place in:

  • Phase 1: Roundabout junction 1 and Roundabout junction 2 on the A530 Middlewich Road - May 2022 – Complete
  • Phase 2: Roundabout junction 3 and Roundabout junction 7 – Complete
  • Phase 3: New Bob Brown Way and Roundabout junction 5 – Complete
  • Phase 4: New Brian Palin Way, New Tottys Hall Way and Roundabout junction 6 - In progress

Current phase

The last phase of works will progress on the new Brian Palin Way and new Tottys Hall Way - which has now been opened. The construction activities will include building new:

  • drainage system under the new road
  • embankments
  • new roundabouts and carriageways
  • boundary fencing works and landscaping

There will still be roadworks taking place within the immediate vicinity of the North West Crewe Package scheme, but these will be managed by third party contractors. As an example. Leighton Hospital will be doing some significant works as part of its redevelopment plans. 

Engagement with the local community

The project team has partnered with local charities to support and provide assistance to events held in Crewe. Information of past and future events can be found within regular newsletter.

Contact information

Email: nwcp@cheshireeast.gov.uk

Page last reviewed: 12 July 2024